TSB: an IT migration that paralysed a bank

UK, 2018. A banking platform migration fails at go-live and disrupts services for months.

In one sentenceA go-live date is a decision, not a plan: TSB worked backwards from the date, and its customers paid for it.

Sector
Retail banking
Country
United Kingdom
Date
April 2018
Duration
Business as usual only by December 2018
Regulatory outcome
£48.65m fine (FCA and PRA, 2022)

Analysis based solely on public information. FZ Consultation was not involved in this incident and has no affiliation with the organizations named.

What happened

  1. 2015–2018

    TSB prepares to move its services from the Lloyds platform to a new platform designed and run by a subsidiary of its parent, Sabadell.

  2. 20–22 April 2018

    The data migrates successfully, but the platform suffers technical failures as soon as it goes live.

  3. Following weeks

    Branch, telephone, online and mobile banking are disrupted; every branch and a large share of 5.2 million customers are affected.

  4. December 2018

    The bank returns to business as usual.

  5. December 2022

    The FCA and PRA impose a £48.65m fine. In 2023 the PRA also fines the former CIO.

What went wrong

According to the public sources listed below.

A schedule worked backwards

According to the regulators, the plan worked back from a target date instead of realistically estimating each stage, even after delays.

Reduced testing

The scope of non-functional testing for digital channels was reduced to one of the two data centres.

Weak supplier oversight

The regulators concluded the bank did not adequately manage the risks of its outsourced IT supplier, even though it was within the group.

Lessons for your organization

  1. 1

    Plan left to right

    Estimate each phase before setting a date, and honestly reassess after every delay.

    Know: measure what stopping would cost
  2. 2

    Test under real conditions

    Load, capacity and failover across every data centre before go-live, with a proven rollback plan.

    Prove: rehearse before the real day
  3. 3

    Oversee critical third parties

    An intra-group supplier is still a third party: ask for evidence, not reassurance. DORA and FCA/PRA rules require it too.

    Regulations

Check on Monday morning

Three questions to put to your own organization this week. If you cannot answer one of them in five minutes, that is your first task.

  1. Take your next big change. Was each phase estimated before the date was fixed?
  2. Is there a rollback you have actually rehearsed, across every data centre?
  3. Ask your most critical IT supplier, even an internal one, for test evidence rather than reassurance.
Rehearse a rollback